Barnes, a global moulding solutions manufacturer, partnered with KSH INFRA to develop a built-to-suit manufacturing facility for their heavy-duty operations. This greenfield project carried a fixed 12-month timeline. While the initial requirement was for 80,000 sq. ft., during the site visit Barnes selected Building B4, factoring in future expansion.
The project demanded extensive structural, utility, and infrastructure provisions, including:
These requirements, defined by Barnes’ global team, were structurally complex and had to be delivered in a phased manner.
KSH INFRA delivered a 180,000 sq. ft. facility meeting Barnes’ operational and technical standards.
Key Deliverables:
Structural Engineering
Electrical Infrastructure
Thermal Insulation
External Utilities & Civil Works